Pending
2
Approved
2
up15%Total Cost Impact
$46,200
| Project | Description | Cost Change | Timeline Change | Status | Date |
|---|---|---|---|---|---|
| Lakewood Custom Home | Add covered patio with outdoor kitchen | +$28,500 | +12 days | Pending | 2026-03-08 |
| Downtown Office Remodel | Upgrade HVAC system to VRF | +$42,000 | +5 days | Approved | 2026-03-01 |
| Harbor View ADU | Switch to engineered hardwood flooring | +$4,200 | No change | Approved | 2026-02-25 |
| Elm Street Renovation | Remove load-bearing wall per structural engineer | +$15,800 | +8 days | Clarification Requested | 2026-03-06 |
| Lakewood Custom Home | Downgrade countertops from quartzite to quartz | -$6,500 | -3 days | Rejected | 2026-02-20 |
| Pine Ridge Development | Add EV charging stations to garages | +$18,000 | +2 days | Pending | 2026-03-10 |