Scheduled
4
Passed
3
up10%Failed
1
Pass Rate
75%
down3%| Project | Type | Status | Scheduled Date | Notes |
|---|---|---|---|---|
| Lakewood Custom Home | Foundation | Passed | 2026-02-10 | No issues found. Rebar placement and footings approved. |
| Lakewood Custom Home | Framing | Scheduled | 2026-03-18 | -- |
| Downtown Office Remodel | Electrical Rough-In | Failed | 2026-03-02 | Junction box in ceiling plenum not rated. Must use listed boxes. |
| Downtown Office Remodel | Electrical Rough-In | Scheduled | 2026-03-16 | Re-inspection after correction |
| Harbor View ADU | Plumbing Rough-In | Passed | 2026-02-22 | All drains tested and approved. |
| Elm Street Renovation | Structural | Passed | 2026-02-28 | Steel beam installation per engineer specs. |
| Pine Ridge Development | Footing | Scheduled | 2026-03-22 | -- |
| Meadow Creek Duplex | Final | Scheduled | 2026-04-05 | Certificate of occupancy pending. |